Work programme

Seven work packages over 36 months

January 2028 to December 2030. 207 person-months; EUR 986,667 total cost, EUR 810,000 requested. WUT leads are proposed.

WP1M1–M36 · 24 PM

Management, quality and ethics

Lead: Warsaw University of Technology (proposed)

Consortium governance, reporting, financial coordination, national interfaces, ethics and data-management oversight; risk and change register. D1.1 management and quality plan M3; D1.2 data management plan and ethics framework M3, updated M12, M24 and M36.

WP2M1–M12 · 29 PM

Cross-sector design and Compacts

Lead: Warsaw University of Technology (proposed)

WUT, the City of Warsaw and AUTh map objectives, sites, barriers and multimodal accessibility, with co-design involving commuters, employers and institutions. D2.1 shared baseline and design protocol M6; D2.2 two draft Compacts M9 and implementation commitments M12.

WP3M1–M30 · 47 PM

Platform and service integration

Lead: Signalton Teknoloji Ltd.

Architecture, secure data interfaces, dashboards, multimodal support, sensor integration and testing. D3.1 architecture and test plan M4; D3.2 core MVP M12; D3.3 participant-service beta M15; D3.4 qualification evidence M30.

WP4M6–M30 · 45 PM

Living Lab deployment and validation

Lead: Aristotle University of Thessaloniki

Site preparation, recruitment, deployment, support and iterative operation in the Warsaw and Thessaloniki labs. D4.1 site-readiness plans M9; D4.2 operational demonstrators M18; D4.3 comparative operational validation M24/M30.

WP5M1–M36 · 25 PM

Outcomes, equity and impact

Lead: Aristotle University of Thessaloniki

Pre-specified mixed-method evaluation, comparison design, data quality, emissions, cost and accessibility analysis, qualitative adoption study. D5.1 evaluation plan M6; D5.2 interim evidence M24; D5.3 final evaluation M36.

WP6M6–M36 · 27 PM

Uptake and exploitation research

Lead: World Gastronomy Network Kft.

Test service and organisational models, costs and willingness to pay; assess access, licensing and procurement routes. D6.1 model options M18; D6.2 two continuation roadmaps and transfer toolkit M36.

WP7M1–M36 · 10 PM

DUT Knowledge Hub and dissemination

Lead: Warsaw University of Technology (proposed)

The designated expert contributes at least five person-months; partners support cross-project synthesis, practitioner exchanges, public outputs and scientific dissemination. D7.1 engagement plan M3; D7.2 cases and briefs M24; D7.3 final synthesis M36.

Phases and milestones

Seven milestones and TRL gates

  1. M3
    MS1 · Baseline and governance

    Versioned TRL 4 evidence package reviewed; roles, risk register and initial data management plan approved; background inventory and access confirmed.

  2. M6
    MS2 · Design and relevant-environment test

    Recruitment feasibility and evaluation plan approved; core data interface validated with real authorised inputs (TRL 5 for the tested subset).

  3. M12
    MS3 · Core demonstration readiness

    Core employer and municipal functions demonstrated in relevant lab settings (TRL 6); Compacts and field safeguards agreed; route and mobile beta at M15.

  4. M18
    MS4 · Operational deployment

    Both labs pass readiness checks: legal and data arrangements, staff training, participants, support, interfaces and measurement; staged release.

  5. M24
    MS5 · Integrated TRL 7

    Operational demonstration in both labs with real authorised users and data; incidents, usability and performance documented against agreed thresholds.

  6. M30
    MS6 · Selected core TRL 8

    Selected modules pass qualification, security, maintainability and user-acceptance tests for their intended use; others keep their demonstrated TRL.

  7. M36
    MS7 · Evidence and continuation

    Final comparative evaluation, two costed continuation plans, transfer toolkit and Knowledge Hub synthesis delivered; owners and next decisions documented.

Pilot design gate

Before deployment, each lab must have an urban-authority interface, anchor employers or institutions, a user or civil-society representative, baseline data and an authorised local lead. No unfunded third-city pilot is on the critical path; reserve institutional sites cover recruitment delays, and the AUTh campus provides a second institutional anchor.